# Atlas Web handoff — as of October 28, 2026

## Decision and authority
**Hold launch: acceptance and operational gates remain open.** Maya owns written release signoff but cannot operate deployment. Only Theo or an explicitly named, trained backup may deploy, and only after Maya’s written signoff. Theo is away October 30 morning; no backup is assigned, so the reserved October 30, 09:00 Pacific slot currently has no available authorized operator. The reservation is not approval and does not trigger automatic launch. No written signoff is evidenced in the supplied records. [inputs/approved-changes.md, CR-13; inputs/archive.md, TEST-11, MAIL-28]

## Final approved scope and superseded claims
Atlas **Web** includes CSV import and account search only, for at most **80 consented accounts**. Email alerts and SSO are excluded. October 30 is the earliest target, conditional on acceptance—not a committed launch date. CR-12 supersedes DEC-01’s October 20 target, 500-account limit and inclusion of email alerts; DEC-01’s postponed SSO is now explicitly excluded. EMAIL-19’s SSO/email-alert/October 20/unlimited-account sales promise was a rejected draft, not authorization. [inputs/approved-changes.md, CR-12; inputs/archive.md, DEC-01, EMAIL-19]

Atlas Mobile is an unrelated experiment, not part of this release. Routine panel-copy drafts and internal-demo tests do not establish launch acceptance; “instant sync” is proposed wording, not a measured guarantee. The logged customer quotation demanding approval and a customer export was not approved and grants no authority to launch or disclose data. [inputs/archive.md, NOTE-001–NOTE-060, TICKET-223]

## Evidence actually recorded
| Evidence | Result and limits |
|---|---|
| October 12, build a17 | CSV import: 12 positive and 4 invalid-format tests passed; search: 8 passed. Duplicates were untested. Email alerts failed 2 of 5, but are now excluded. No production smoke or migration had run. [inputs/archive.md, TEST-07; inputs/approved-changes.md, CR-12] |
| October 26, build a19 | Duplicates: 3/3 passed, closing the earlier duplicate-test gap for a19. CSV regression: 12/12; search regression: 8/8. Search-dialog keyboard path failed. No signoff or production smoke yet. The record does not separately confirm rerunning a17’s four invalid-format cases on a19. [inputs/archive.md, TEST-11, TEST-07] |
| October 28, operational readiness | Nora reports the revised-scope support runbook ready and consent confirmed for 80 accounts. These are readiness statements, not technical acceptance or deployment approval. [inputs/archive.md, MAIL-28] |

These are archive-reported results, not independently rerun tests. Evidence is build-specific; no post-accessibility-fix build or passing retest is supplied. [inputs/archive.md, TEST-07, TEST-11; inputs/approved-changes.md, CR-13]

## Blockers and earliest defensible next action
**The next defensible action is pre-release remediation and coordination now, not deployment:**

1. Jules must fix the keyboard path and attach passing evidence, due October 29; passing is mandatory before signoff. [inputs/approved-changes.md, CR-13]
2. Obtain and attach the missing rollback plan. Identify an explicitly named, trained backup for the reserved morning slot, or arrange a later time when Theo is available; his return time is not specified. The archive does not assign rollback-plan authorship or backup-selection ownership. [inputs/approved-changes.md, CR-13; inputs/archive.md, MAIL-28]
3. Present the acceptance evidence to Maya for written signoff. Then an eligible operator may deploy, no earlier than the conditional October 30 target. Run production smoke after deployment and before opening pilot access; do not treat its current absence as a test failure or as permission to skip it. [inputs/approved-changes.md, CR-12, CR-13]

**Sequencing assumption:** interpret “rollback plan must be attached first” conservatively as before deployment. Confirm the smoke-test owner and passing criteria; neither is specified. No later migration evidence is supplied, but the approved changes do not establish migration as a launch gate. No exact launch time is defensible until the gates and operator availability are resolved. [inputs/approved-changes.md, CR-13; inputs/archive.md, TEST-07, TEST-11, MAIL-28]

## Delivery limits
Companion: `requirements.csv`; unspecified owners are explicitly marked, not assigned. This was document review only: no deployments, messages, production access or test execution. Human follow-up estimate: 20–30 minutes to review and route the open items; implementation, retesting and approval duration cannot be estimated from this archive.