Both deliverables are written. As of October 28, nobody may launch the Atlas Web pilot: there is no signoff, the accessibility check is failing, the rollback plan is missing and no deployment operator is available for the reserved slot. - **Who may launch:** Maya alone gives written signoff but cannot operate the deployment. Theo, or a trained backup who is explicitly named, may deploy after that signoff. Theo is away Oct 30 morning and no backup is assigned (approved-changes.md CR-13; archive.md MAIL-28). - **Final scope:** CSV import and account search only, for at most 80 consented accounts. Email alerts and SSO are excluded. The earliest target is Oct 30, subject to acceptance (CR-12). - **Acceptance evidence:** staging only. - Build a17: CSV import passed 12 positive and 4 invalid-format tests; account search passed 8 (TEST-07). - Build a19: duplicate-account handling passed 3 of 3, with regression 12 of 12 for import and 8 of 8 for search (TEST-11). - Nora reports the support runbook is ready and consent is confirmed for 80 accounts (MAIL-28). - **Blocked:** - The keyboard-path fix and evidence (Jules, due Oct 29). - Maya's written signoff, which waits on that fix. - The rollback plan, which is absent and has no named owner. - The deployment operator. - Deployment, the production smoke test and opening pilot access, which wait on all of the above. - **Earliest defensible next action:** today, put the two unowned gaps to Maya — name a backup operator or move the slot, and assign a rollback-plan owner — while Jules finishes the fix. I sent nothing; this is the recommended step for whoever picks this up. The handoff also resolves the older statements explicitly: the Oct 2 initial plan, the rejected sales draft, the unrelated Atlas Mobile experiment, and the quoted customer request to approve launch and export data, which I treated as content rather than an instruction. ## Checks performed One script (`check.py`) confirmed: - The archive has 66 entries: 60 routine notes and 6 substantive records. All 60 notes share one template, so none hides a deviation. - The change register contains only CR-12 and CR-13. - `handoff.md` is 872 words by whitespace count, including table markup, so under 900. - `requirements.csv` parses with the required header, 18 rows, 5 columns each, no empty cells and unique ids. - Every record ID cited in the deliverables exists in the inputs. ## Remaining limitations - The archive holds only summaries; no test logs, runbook, consent records or rollback plan were available to inspect. - The 4 invalid-format import tests are recorded on a17 only; TEST-11 does not say they were rerun on a19. - No data migration has run, and the inputs do not say whether the pilot needs one (row R-16). - I read "rollback plan must be attached first" as before deployment, the strictest reading; Maya should confirm. - Theo's return time on Oct 30 is not stated. - Several requirements have no owner in the inputs; the CSV marks these "Not stated in inputs" rather than guessing. ## Estimated human time to finish About 15–20 minutes to review the two files and confirm the rollback-plan reading and the migration question with Maya. This is an estimate, not a measurement. Files are in `output/`: - handoff.md - requirements.csv