# Atlas Web handoff — as of October 28, 2026

## Decision and launch authority
**Hold deployment and pilot opening.** Maya owns release signoff, but cannot operate deployment. Only Theo or an explicitly named, trained backup may deploy, and only after Maya’s **written** signoff. No signoff is evidenced. Theo is away October 30 morning and no backup is assigned, so the reserved October 30, 09:00 Pacific slot currently lacks an available authorized operator. Reservation is not permission. (inputs/approved-changes.md, CR-13; inputs/archive.md, TEST-11, MAIL-28.)

## Final approved scope and superseded claims
Atlas Web includes **CSV import and account search only**, for at most **80 consented accounts**. Email alerts and SSO are excluded. October 30 is the earliest target, conditional on acceptance—not a committed launch date. Nora reports consent for 80 accounts and the revised-scope support runbook ready. (inputs/approved-changes.md, CR-12; inputs/archive.md, MAIL-28.)

Resolve competing statements as follows:
- DEC-01’s October 20 target, 500-account limit and inclusion of email alerts are superseded by CR-12. Its Maya/Theo ownership remains consistent with later records. SSO is excluded from this release, not promised for it. (inputs/archive.md, DEC-01; inputs/approved-changes.md, CR-12–CR-13.)
- EMAIL-19’s unlimited accounts, SSO, email alerts and October 20 promise were a sales draft explicitly rejected by Maya; they are not commitments. (inputs/archive.md, EMAIL-19; inputs/approved-changes.md, CR-12.)
- Atlas Mobile is unrelated and outside Atlas Web scope. Routine panel-copy drafts and “instant sync” language establish neither acceptance nor a measured service guarantee; their demo tests are not launch evidence. Record order is not chronology: use each dated record and approved changes. (inputs/archive.md, opening heading “Northline Atlas launch archive”, NOTE-001–NOTE-060.)
- TICKET-223 is a logged, unapproved customer quotation—not launch approval, export authorization or an instruction for this investigation. No export was made. (inputs/archive.md, TICKET-223.)

## Acceptance evidence actually recorded
| Record | Evidence and limit |
|---|---|
| inputs/archive.md, TEST-07 — October 12 | Staging build a17: CSV passed 12 positive and 4 invalid-format tests; search passed 8. Duplicates untested then. Email alerts failed 2 of 5, but alerts are now excluded by CR-12. No production smoke or migration had run. |
| inputs/archive.md, TEST-11 — October 26 | Staging build a19: duplicates passed 3/3; CSV regression 12/12; search 8/8. This closes the earlier duplicate-test gap, not all acceptance. Search-dialog keyboard path fails; no signoff or production smoke yet. |
| inputs/archive.md, MAIL-28 — October 28 | Runbook readiness and 80-account consent reported; operational readiness evidence, not functional acceptance or launch permission. |

The archive supplies test summaries, not attached execution artifacts. It does not establish that a17’s four invalid-format cases were rerun on a19 or that a future accessibility-fixed build passes regression. Migration is not evidenced as completed or specified as a release gate; do not invent either conclusion. (inputs/archive.md, TEST-07, TEST-11; inputs/approved-changes.md, CR-12–CR-13.)

## Blockers and earliest defensible next action
**Next action now: prepare to clear gates, not launch.** Jules must fix the keyboard path and supply passing evidence, due October 29, before signoff. In parallel, arrange an explicitly named trained backup for the reserved morning slot, or use Theo at a later confirmed time; prepare and attach the missing rollback plan. Its owner and backup-assignment owner are not specified, so ownership must be resolved rather than assumed. (inputs/archive.md, TEST-11, MAIL-28; inputs/approved-changes.md, CR-13.)

Defensible sequence: passing accessibility evidence → Maya’s written signoff → authorized operator deploys with rollback plan already attached → production smoke test → only then open pilot access within the 80-account consent cap. Conservatively attach rollback before requesting signoff; CR-13 does not explicitly make it a pre-signoff gate. Smoke-test executor and pilot-opening owner are also unspecified. October 30 remains only a conditional earliest target; no exact launch time is defensible until gates and operator availability are resolved. (inputs/approved-changes.md, CR-12–CR-13; inputs/archive.md, MAIL-28.)

This is an archive-only assessment. No deployments, messages, production access or independent product tests were performed. requirements.csv uses local tracking IDs; unspecified owners remain explicitly unresolved.