# Field Notes webinar — Decision log
Status as of 2026-10-20 10:00 Pacific. Draft prepared by the coordinator. Nothing has been sent.
Precedence rule used: an explicit, dated approval overrides earlier instructions on the same point. The most recent approval is CR-07 (Priya, Oct 19 16:00 PT).

## 1. Agreed decisions (explicitly approved)
| # | Decision | Supersedes | Source |
|---|---|---|---|
| D1 | Event is **Oct 30, 2026, 11:00 PT**. This date is final. | Oct 29 10:00 PT (brief) | 03-email-thread.txt (Priya Oct 18 09:00); confirmed final in 04-approved-change.md CR-07 |
| D2 | Duration stays at 45 minutes | — | 01-original-brief.md; 03-email-thread.txt (Priya Oct 18) |
| D3 | Platform stays **MeetRoom** | Jonah's StreamHall proposal (never decided) | 03-email-thread.txt (Priya Oct 18) |
| D4 | Attendee cap is **80**, the limit of our plan | 120 (brief) | 03-email-thread.txt (Priya Oct 18) |
| D5 | Entry is **free**. Budget cap stays at CAD 1,200 | Mei's paid-ticket proposal (never approved) | 03-email-thread.txt (Priya Oct 18) |
| D6 | All launch copy stays in draft until the platform test passes | — | 03-email-thread.txt (Priya Oct 18); 02-meeting-notes.md |
| D7 | Captions are a launch requirement. Registration opens **Oct 23 09:00 PT** only if the captions and capacity tests pass on Oct 22 | — | 02-meeting-notes.md; 04-approved-change.md CR-07 |
| D8 | No recording or replay promise may appear without written speaker consent. If there is no consent, the event runs live-only | Brief: "record the event and email replay to all registrants" | 04-approved-change.md CR-07 |
| D9 | Paid advertising is on hold until a separate written campaign approval exists. Speaker confirmation alone does not authorize spending | Oct 16 note: "no paid campaign until the speaker confirms" | 04-approved-change.md CR-07 |
| D10 | Owners and deadlines: Jonah, landing corrections, Oct 21 17:00. Mei, invitations, Oct 22 12:00. Alex, slides, Oct 27 17:00 (was Oct 26), and consent follow-up, Oct 21. Priya, final launch approval, Oct 22 17:00, and test-owner assignment, Oct 21 12:00 | Brief deadlines (Jonah Oct 21, Mei Oct 22, Alex Oct 26) | 04-approved-change.md CR-07 |
| D11 | Publishing the landing page needs Priya's approval (not changed later) | — | 01-original-brief.md |

## 2. Facts reported (not decisions)
- The guest speaker confirmed Oct 30 11:00 PT and consents to **live attendance only**. No recording or replay consent has been given yet. (03-email-thread.txt, Alex Oct 18 12:30)
- The landing draft is ready but still contains the original replay promise. Jonah offered to update the date and cap on Oct 19. The inputs do not confirm he did. (03-email-thread.txt, Jonah Oct 19 08:10)
- Mei can finish draft copy without choosing recipients. (05-open-questions.txt, Oct 20 09:30)

## 3. Proposals, not adopted
- P1: StreamHall for possibly better captions (Jonah, Oct 16). Not decided, and in effect closed by D3. (02-meeting-notes.md)
- P2: Paid tickets (Mei, Oct 16). Not approved, and in effect closed by D5. (02-meeting-notes.md)
- P3 (coordinator proposal): use live-only wording in all copy now and add replay wording only after written consent. CR-07 makes live-only the default, but nobody has approved the exact replacement wording.
- P4 (coordinator proposal): settle U2 and U4 on Oct 20–21, so Jonah's and Mei's deadlines are not blocked. No one has agreed to this.

## 4. Unresolved issues (no answer invented)
| # | Issue | Type | Needed by | Source |
|---|---|---|---|---|
| U1 | No one owns the platform test yet. Priya must assign one | Ownership | Oct 21 12:00 PT | CR-07 |
| U2 | Nobody is named to approve the replacement replay wording Jonah asked about | Ownership / content | Before Oct 21 17:00 (Jonah's deadline) | 03-email-thread.txt; CR-07 |
| U3 | Recording and replay consent is pending. Alex's Oct 21 date is for the follow-up. No date is set for a final answer, and no one owns recording setup or the replay email if consent comes | Consent / ownership | Not set | 03-email-thread.txt; CR-07 |
| U4 | Invitation recipients are undecided: all 600 newsletter subscribers or only the webinar opt-in segment. The consent scope of the list can't be checked from the inputs | Consent | Before invitations go out | 05-open-questions.txt |
| U5 | No one is named to publish the page or send invitations, and no send time is set | Ownership / scheduling | Oct 23 09:00 PT | CR-07 (silent) |
| U6 | No test time is set for Oct 22. It must finish before Priya's 17:00 approval. Mei's 12:00 invitation deadline falls before the test result | Scheduling | Oct 22 | CR-07 |
| U7 | There is no fallback if the Oct 22 test fails, because registration can't open Oct 23. No alternative date or process is defined | Scheduling | Oct 22 | CR-07 |
| U8 | The MeetRoom plan cost and other spend against the CAD 1,200 cap are not recorded in the inputs | Budget | — | 01-original-brief.md |

## 5. Assumptions
- All times are Pacific, 2026.
- CR-07 says Mei "owns invitations due Oct 22 at 12:00". I read this as draft copy, because D6 keeps all copy in draft until the test passes and the test result comes after 12:00. Sending happens only after D6/D7 conditions are met and Priya approves (A08).
- Invitations are not sent before registration opens (Oct 23 09:00). This is my assumption, not a stated rule.
- Settling the recipient list (A05) is not listed as a prerequisite for launch approval (A08), because no source makes it one. It does block sending (A10).

## 6. Recommended sequence of next steps (IDs from action-plan.csv)
1. **Oct 20–21 a.m.:** Priya assigns the test owner (A01, by 12:00 Oct 21). Someone confirms the live-only replacement wording (A03). Priya decides the recipients and checks consent scope (A05). Alex sends the consent request (A02, by Oct 21).
2. **Oct 21, 17:00:** Jonah finishes the landing corrections in draft (A04).
3. **Oct 22:** Mei's invitation drafts are due at 12:00 (A06). The test owner runs the captions and 80-seat test (A07, time TBD). Priya gives launch approval by 17:00 (A08). If the test fails, registration does not open; next steps need a decision (U7).
4. **Oct 23, 09:00:** publish and open registration (A09). Then send invitations to the approved list (A10, once A05 is settled).
5. **Before Oct 30:** apply the consent outcome (A11). Alex's slides are due Oct 27 at 17:00 (A12). Paid ads stay on hold (A13).
6. **Oct 30, 11:00:** live event (A14). Afterwards, send the replay email only with written consent (A15).